A development site can look promising on paper when the location is right, the planning controls appear workable, the land area suits the proposed development, and the numbers seem to stack up.
But before committing to a site, there is another question worth asking:
What is happening from an engineering and infrastructure perspective?
The answer can help determine how much of the site can ultimately be developed, how the project needs to be staged and what it may cost to deliver.
This is where land development feasibility becomes important.
Looking at engineering constraints early can help developers better understand what they are buying and identify issues while there is still an opportunity to respond to them.
Here are eight areas worth looking into before committing to a development site.
1. Can the site actually be serviced?
Water, sewer, electricity and telecommunications infrastructure are fundamental to most developments, but their availability and capacity should not be taken for granted.
An existing service nearby does not necessarily mean the development can simply connect to it or that sufficient capacity is available.
Early investigations may need to consider:
- The location of existing water and sewer infrastructure, and connection options
- Water, sewer and electricity network capacity, including potential substations or kiosks
- Connection points and NBN telecommunications servicing
- Required extensions or upgrades
- Easements and infrastructure corridors
- The timing of future authority infrastructure
- Whether works need to extend beyond the development boundary
The answers can drive both development costs and timing.
For larger projects in particular, infrastructure delivery can also affect development staging. A site might have strong long-term development potential but require additional infrastructure before certain areas can proceed.
Understanding this early provides a much clearer picture of the site’s practical development pathway.
2. What does stormwater do when it reaches the site?
Stormwater is much more than finding somewhere for runoff to go.
Existing drainage conditions, flood behaviour, overland flow paths, downstream infrastructure and water quality requirements can all shape the development of a site.
Depending on the location, investigations may need to consider matters such as:
- Flood levels and flood risk, including Land Subject to Inundation Overlay (LSIO), Floodway Overlay (FO) and Special Building Overlay (SBO) controls where applicable
- Existing drainage infrastructure
- Overland flow paths
- Retarding basins and wetlands
- Water sensitive urban design
- Stormwater treatment requirements
- Downstream discharge constraints
- Melbourne Water Development Services Schemes (DSS) or relevant catchment management authority (CMA) requirements in regional areas
These considerations can have a direct impact on the development layout.
Land may need to be allocated to drainage infrastructure. Nominated flood levels and required freeboard may dictate minimum floor levels and the amount or location of fill. Finished surface levels may need to change. Roads and lots may need to respond to overland flows or flood conditions.
For that reason, stormwater should be considered as part of the development site feasibility assessment, rather than being left until detailed design.
DPM’s water resources work includes areas such as stormwater management, flood control, drainage strategies and water quality, reflecting how closely water planning relates to broader land development decisions.
3. What is the site's topography telling you?
Two parcels of land of a similar size can present very different engineering challenges.
The natural slope of a site can determine road grades, lot levels, drainage, earthworks, retaining structures and the overall amount of usable land.
A relatively flat site may appear straightforward but could present drainage challenges.
A steep site may provide natural drainage opportunities but require more significant earthworks, retaining walls or careful road design.
It’s important to understand existing levels early and consider how they interact with the proposed development.
Earthworks can also have a substantial flow-on effect. Changing levels in one part of a site may affect drainage, neighbouring properties, road connections or the amount of material that needs to be imported or removed.
Rather than looking at topography as an isolated issue, it should form part of the broader land development feasibility assessment.
4. How will vehicles get in and out?
Access is another area that can appear simple at first glance.
A site could have a road along its boundary, but that does not necessarily mean the existing road network can accommodate the proposed development without further works.
Depending on the scale and location of the project, consideration may need to be given to:
- Proposed site access
- Existing road conditions
- Intersection requirements
- Road widening or upgrades
- Connections into surrounding road networks
- Pedestrian and cycling infrastructure
- Future arterial roads and Public Acquisition Overlay (PAO) reservations for planned road corridors
- Access requirements for different stages of the development
A requirement for a new intersection or significant road upgrade can materially change both project cost and programme. Where works involve arterial roads or intersections under the Department of Transport and Planning (DTP), VicRoads accreditation can be an important consideration in selecting suitably qualified engineering partners. DPM’s VicRoads accreditation supports its involvement in these types of road and access projects.
For larger residential, commercial and industrial developments, understanding these requirements before the layout is advanced can also prevent substantial redesign later.
DPM’s civil engineering capabilities include land development, road upgrade works and intersection upgrade works alongside water, sewer and drainage infrastructure.
5. What is already on, under or planned for the land?
One of the most important questions during a development site assessment is not simply what you want to put on the land, but what is already there.
Existing conditions can include:
- Easements
- Sewer and water infrastructure
- Stormwater assets
- Electricity and telecommunications infrastructure
- Gas services
- Existing buildings or structures
- Waterways and drainage corridors
- Roads or accessways
There may also be infrastructure that does not exist yet but has already been planned.
Future roads, drainage assets, trunk services or infrastructure reservations can constrain how land can be developed.
Identifying these constraints early allows the project team to understand what land may genuinely be available for development and what areas need to be accommodated within the overall plan.
Sometimes a constraint simply needs to be designed around. In other cases, it can fundamentally change the development strategy.
6. What will councils and authorities require?
Land development rarely involves one approval body.
Depending on the project, developers may need to work with local councils, water authorities and other government agencies, each with their own technical requirements and approval processes.
These requirements can shape:
- Infrastructure standards
- Drainage
- Road design
- Service connections
- Development staging
- Documentation
- Construction
- Asset handover
Early consultation can help clarify what is likely to be required before the project progresses too far. Financial obligations should also be checked, including Development Contributions Plan (DCP) or Infrastructure Contributions Plan (ICP) levies, and applicable drainage scheme contributions. These charges can materially alter acquisition feasibility and should be considered alongside the cost of physical infrastructure works.
This is particularly important where a development relies on infrastructure outside the site or requires coordination between several stakeholders.
An engineering solution might work technically, but it also needs to respond to the standards and requirements of the authorities that will ultimately review or accept it.
7. Can the development be staged practically?
For larger developments, the question isn’t only what can be developed?
It’s also what order can it be delivered in?
Development staging can be dictated by infrastructure availability, drainage, road access, earthworks, authority approvals and the location of connection points.
A proposed first stage may look logical from a sales or planning perspective, but prove difficult to service independently.
Alternatively, bringing forward a particular piece of infrastructure may unlock several future stages.
Considering staging during the feasibility process can help connect the engineering strategy with the commercial strategy for the project.
This is where early coordination between engineering, project management and development planning becomes particularly valuable.
8. How do all these constraints affect each other?
This is perhaps the most important check of all.
Development constraints rarely exist independently. A drainage requirement can dictate site levels. Those levels shape road grades and lot design. A sewer connection can determine which area is practical to develop first. A road upgrade can delay a stage. Authority requirements may add to both design complexity and cost.
Looking at each issue separately may provide only part of the picture. A thorough land development feasibility study should bring these considerations together so that developers can understand how the site operates as a whole.
Bringing DPM’s Land Development, Infrastructure, Water Resources, and Project & Construction Management expertise together helps identify opportunities for more efficient land use, as well as risks that could affect project success.
The goal isn't to find a site with no constraints
Almost every development site has constraints.
The presence of drainage infrastructure, difficult levels or servicing requirements does not automatically make a development unviable.
The important thing is understanding those constraints early. Once they are known, the project team can investigate possible solutions, test different development scenarios and understand their potential impact on cost, yield, programme and staging.
Discovering the same issue after significant design work has already been completed generally leaves fewer options available. That is why early engineering investigations can be valuable even before a site has been purchased or a development layout has been finalised.
What should a land development feasibility assessment include?
The exact scope will depend on the site and proposed development, but an early engineering review may consider:
- Existing site conditions and topography
- Water, sewer, electricity and NBN servicing
- Stormwater drainage, flood overlays, nominated flood levels and freeboard
- Road access and surrounding infrastructure
- Existing easements, utilities and planning overlays, including road reservations
- Future infrastructure requirements
- Council and authority requirements, including DCP/ICP levies and drainage contributions
- Preliminary development staging
- Geotechnical conditions such as reactive soils, rock and groundwater, with specialist input where required
- Potential contaminated land and the need for specialist environmental assessment
- Engineering opportunities and constraints
- Potential infrastructure or development costs
The objective is not necessarily to complete every investigation upfront. It is to identify the issues most likely to affect the development and determine where further investigation is warranted before major decisions are made.
When should you engage a land development engineer?
Ideally, engineering input should begin while there is still flexibility in the project. That may be during acquisition due diligence, preparation of an initial development concept or the early feasibility phase.
For developers assessing a potential acquisition, early involvement allows engineering considerations to form part of the decision-making process rather than becoming something that needs to be addressed after the site has already been secured.
It can also provide useful information for planners, surveyors, architects, developers and other consultants as the development concept progresses.
Land development feasibility is about understanding the full picture
Buying development land involves much more than assessing location and available area.
The infrastructure surrounding the site, the way water moves through it, its levels, access, servicing and the requirements of councils and authorities all help determine what the development eventually looks like.
Understanding those factors early can help project teams make better-informed decisions and develop a more realistic pathway from acquisition through to construction.